Question: Given the following information regarding a project: Activity Duration Predeccors a 3 none b 1 none c 3 a d 4 a e 4 b
Given the following information regarding a project:
| Activity | Duration | Predeccors |
| a | 3 | none |
| b | 1 | none |
| c | 3 | a |
| d | 4 | a |
| e | 4 | b |
| f | 5 | b |
| g | 2 | c, e |
| h | 3 | f |
Which of the following is NOT a path in the network?
What is the critical path?
How long will it take to complete the project?
What is the ES for activity g?
What is the LF for activity a?
What is the LF for activity b?
What is the LF for activity d?
What is the LF for activity g?
What is the LF for activity h?
What is the slack for activity b?