Question: Given the following information regarding a project: Activity Duration Predecessors a 3 None b 1 None c 3 a d 4 a e 4 b
Given the following information regarding a project:
Activity
Duration
Predecessors
a
None
b
None
c
a
d
a
e
b
f
b
g
c e
h
f
Which of the following is NOT a path in the network?
ad
acg
bcg
beg
bfh
points
Question
What is the critical path?
ad
acg
bcg
beg
bfh
points
Question
How long will it take to complete the project?
points
Question
What is the ES for activity g
points
Question
What is the LF for activity a
points
Question
What is the LF for activity b
points
Question
What is the LF for activity d
points
Question
What is the LF for activity g
points
Question
What is the LF for activity h
points
Question
What is the slack for activity b
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock