Question: Given the following information regarding a project: Activity Duration Predecessors a 2 None b 3 None c 2 a d 4 a , b e
Given the following information regarding a project:
Activity Duration Predecessors
a None
b None
c a
d a b
e c
f c
g d e
h f g
Which of the following is NOT a path in the network?
acfh
acegh
adgh
bdgh
bdeh What is the LF for activity h