Question: Given the following information regarding a project: Activity Duration Predecessors a 2 None b 3 None c 2 a d 4 a , b e

Given the following information regarding a project:
Activity Duration Predecessors
a 2 None
b 3 None
c 2 a
d 4 a, b
e 4 c
f 3 c
g 5 d, e
h 2 f, g
Which of the following is NOT a path in the network?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-h What is the LF for activity h?
7
8
10
13
15