Question: Given the following information regarding a project: ActivityDurationPredecessorsa 2 Noneb 3 Nonec 2 ad 4 a , be 4 cf 3 cg 5 d ,

Given the following information regarding a project:
ActivityDurationPredecessorsa2Noneb3Nonec2ad4a, be4cf3cg5d, eh2f, g
Which of the following is NOT a path in the network?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-h
1 points
Question 8
What is the critical path?
a-c-f-h
a-c-e-g-h
a-d-g-h
b-d-g-h
b-d-e-g
1 points
Question 9
How long will it take to complete the project?
4
9
10
13
15
1 points
Question 10
What is the LS for activity a?
0
1
3
4
5

Step by Step Solution