Given the following information regarding a project:
ActivityDurationPredecessorsaNonebNonecada becfcgd ehf g
Which of the following is NOT a path in the network?
acfh
acegh
adgh
bdgh
bdeh
points
Question
What is the critical path?
acfh
acegh
adgh
bdgh
bdeg
points
Question
How long will it take to complete the project?
points
Question
What is the LS for activity a