Question: Given the following information regarding a project involving an initial public offering ( IPO ) : Activity Duration ( wks ) Preceding activities a .

Given the following information regarding a project involving an initial public offering (IPO):
Activity Duration (wks) Preceding activities
a. Check feasibility 3
b. Determine funding 1
c. Find possible banks 3 a
d. Select two possibles 4 a
e. Interview two banks 4 b
f. Analyze funding costs 5 b
g. Determine chance of success 2 c, e
h. Sign contract 3 f
a) Draw the network.
b) What is the critical path?
c) When will the offering be available (end of the project)?
d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks?
Three extra weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!