Question: Given the following information regarding a project involving an initial public offering ( IPO ) : Activity Duration ( wks ) Preceding activities a .
Given the following information regarding a project involving an initial public offering IPO:
Activity Duration wks Preceding activities
a Check feasibility
b Determine funding
c Find possible banks a
d Select two possibles a
e Interview two banks b
f Analyze funding costs b
g Determine chance of success c e
h Sign contract f
a Draw the network.
b What is the critical path?
c When will the offering be available end of the project
d What is the effect on the project if activity e approvals takes an extra week? Two extra weeks?
Three extra weeks?