Question: Given the following information regarding a project concerning an initial public offering (IPO) project: Activity Description Expected Time (weeks) Immediate Predecessors A Check feasibility 3

Given the following information regarding a project concerning an initial public offering (IPO) project:

Activity

Description

Expected Time (weeks)

Immediate Predecessors

A

Check feasibility

3

None

B

Determine funding

1

None

C

Find possible banks

3

A

D

Select two possible banks

4

A

E

Interview two banks

4

B

F

Analyze funding costs

5

B

G

What chance of success?

2

C, E

H

Sign contract

3

F

I

End Project

0

D, G, H

  1. Use Microsoft Word drawing tools to draw the network diagram for the project. Note: Copy and paste the node (circle) given below to duplicate nodes. Type the activity symbol and time inside the node (circle). Go to insert/shapes and select arrow. Use the arrow to connect nodes as per the precedence relationships.

  1. Identify all paths from beginning to finish nodes. Determine the critical path. Note: Show all steps and calculations.

  1. Identify the critical activities.

  1. Determine the project duration.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!