Question: Meredith Problem 8-22 Given the following information regarding a project concerning an initial public offering (IPO) project: Activity Description Expected Time (weeks) Immediate Predecessors A
Meredith Problem 8-22
Given the following information regarding a project concerning an initial public offering (IPO) project:
Activity | Description | Expected Time (weeks) | Immediate Predecessors |
A | Check feasibility | 3 | None |
B | Determine funding | 1 | None |
C | Find possible banks | 3 | A |
D | Select two possible banks | 4 | A |
E | Interview two banks | 4 | B |
F | Analyze funding costs | 5 | B |
G | What chance of success? | 2 | C, E |
H | Sign contract | 3 | F |
I | End Project | 0 | D, G, H |
- Use Microsoft Word drawing tools to draw the network diagram for the project. Note: Copy and paste the node (circle) given below to duplicate nodes. Type the activity symbol and time inside the node (circle). Go to insert/shapes and select arrow. Use the arrow to connect nodes as per the precedence relationships.
2. Identify all paths from beginning to finish nodes. Determine the critical path. Note: Show all steps and calculations.
3. Identify the critical activities.
4. Determine the project duration.