Question: Given the following network, determine the first activity to be crashed by the following priority rules: (a) Shortest task first (b) Minimum slack first (c)
Given the following network, determine the first activity to be crashed by the following priority rules:
(a) Shortest task first
(b) Minimum slack first
(c) Most critical followers
(d) Most successors