Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITYE. table [ [ Activity , Duration,Predecessor,ES , EF

Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITYE.
\table[[Activity,Duration,Predecessor,ES,EF,LS,LF,SLACK],[A,2,-,0,2,0,2,0],[B,10,A,2,12,2,12,0],[C,8,A,2,10,6,14,4],[D,7,B,12,19,12,19,0],[E,5,B, C,12,17,,,],[F,5,D, E,,,,,],[G,4,E,17,21,,,]]
 Given the following partially completed Project Activity Description and Network Diagram,

Step by Step Solution

There are 3 Steps involved in it