Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. EF LS LF SLACK 2 0 2 0

Given the following partially completed Project
Given the following partially completed Project
Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. EF LS LF SLACK 2 0 2 0 2 11 U Activity Duration Predecessor ES A 2 0 B 9 A 2 5 A 2 D 7 B 11 E B, C 11 F 6 D, E G 5 E 13 0 9 11 16 11 7 18 13 11 18 0 2. 18 2 11 11 18 B, 9 D, 7 F. 6 11 11 18 0 START A, 2 FINISH 11 13 13 18 0,5 E, 2 G, 5 11 16