Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITYE. table [ [ Activity , Duration,Predecessor,ES , EF

Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITYE.
\table[[Activity,Duration,Predecessor,ES,EF,LS,LF,SLACK],[A,2,-,0,2,0,2,0],[B,9,A,2,11,2,11,0],[C,5,A,2,7,11,16,9],[D,7,B,11,18,11,18,0],[E,2,B, C,11,13,,,],[F,6,D, E,,,,,],[G,5,E,13,18,,,]]
 Given the following partially completed Project Activity Description and Network Diagram,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!