Question: Given the following PERT chart, identify the tasks in the critical path. Each task with a preceding arrow is dependent on the completion of that

Given the following PERT chart, identify the

Given the following PERT chart, identify the tasks in the critical path. Each task with a preceding arrow is dependent on the completion of that preceding task before it can start Joists Floor Rough Begin 3 days 4 days 7 days Joists Foundation Basement Rafters Roof Trim 3 days 4 days 4 days 5 days 6 days 5 days Walls Landscape End 5 days 4 days