Question: Given the following product structure of A; explode, offset and determine the gross and net requirements. All lead times (LT) are in weeks and the

Given the following product structure of A;

Given the following product structure of A; explode, offset and determine the gross and net requirements. All lead times (LT) are in weeks and the quantities required are shown in parentheses. The MPS calls for 700 units of product A, to be delivered in week 12. The company has in hand 300 units of each of the components C and E. Determine the order release data for all necessary orders. A LT=4 B(1400) C(1400) LT = 3 D(4200) LT = 2 E(2800) LT = 2 F(1400) LT = 4