Question: Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic A 10 12 14 B 8 10 20 D 8 11 15

Given the following project activities. TIME IN

Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic A 10 12 14 B 8 10 20 D 8 11 15 E 17 28 30 The expected time for activity E is (in days) 0 17 4.69 136 26.5