Question: QUESTION 8 Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic 10 Cove 006 14 10 20 00 11 15 28

QUESTION 8 Given the following project
QUESTION 8 Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic 10 Cove 006 14 10 20 00 11 15 28 The expected time for activity E is (in days) 30 O 17 4.69 o 136 26.5