Question: Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic 10 20 B 8 C6 15 28 The variance of activity B

Given the following project activities. TIME IN

Given the following project activities. TIME IN DAYS Activity Optimistic Most Likely Pessimistic 10 20 B 8 C6 15 28 The variance of activity B is (in days) E 30 024