Question: Given the following project: Activity Predecessor Resource A B D Duration (week) 3 2 4 A 6 3 4 2 3 2 3 2 3

Given the following project: Activity Predecessor

Given the following project: Activity Predecessor Resource A B D Duration (week) 3 2 4 A 6 3 4 2 3 2 3 2 3 E F G H 4 4 1 1 B A, B B, C F,H E E D,K IJ G K L M N 2 3 2 3 8 3 5 4 2 2 Assuming that the resource pool is limited to seven, develop a resource-limited schedule using the sequential heuristic and the following rules. (20 pts.) Earliest start time Smallest duration Minimum slack Maximum resource level OOOO