Question: Given the following project data: a) Compute the slope and maximum crash time for each activity b) Compute the total direct cost for each project

Given the following project data: a) Compute the slope and maximum crash time for each activity b) Compute the total direct cost for each project duration c) If the indirect cost for each projoct duration aro S200 (25 time units), 5150 (24 time units). S100 (23 timo units) and 550 (22 time units). computo the total project cost for each duration and writo it in Tablo 2 d) What is the optimum cost-timo schodulo for tho projoot? Then, use the results to complete the tables provided below. Activity Direct cost ID Normal Crash Time Cost Time Cost 4 2003 260 14 50 13 60 7 120 7 220 00 230 4 262 6 90 5 h20 3 3002 305 4 140 4 140 Given the following project data: a) Compute the slope and maximum crash time for each activity b) Compute the total direct cost for each project duration c) If the indirect cost for each projoct duration aro S200 (25 time units), 5150 (24 time units). S100 (23 timo units) and 550 (22 time units). computo the total project cost for each duration and writo it in Tablo 2 d) What is the optimum cost-timo schodulo for tho projoot? Then, use the results to complete the tables provided below. Activity Direct cost ID Normal Crash Time Cost Time Cost 4 2003 260 14 50 13 60 7 120 7 220 00 230 4 262 6 90 5 h20 3 3002 305 4 140 4 140
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
