Question: Given the following project Dur Act Pred Res (days) worker) 7 2 B 5 1 9 5 D AB 7 3 E B,C 6 6

Given the following project Dur Act Pred Res

Given the following project Dur Act Pred Res (days) worker) 7 2 B 5 1 9 5 D AB 7 3 E B,C 6 6 DE 3 ANOM Which of the following is the correct daily resource and cumulative resource table. Select one: Daily Worker 8 7 8 4 S 7 9 15 Cum Resource 8 15 23 32 38 42 O 5 a. 9 7 15 Daily Worker 8 7 8 9 6 4 5 7 14 15 20 Cum Resource 40 14 16 45 6 12 5 9 14 15 O b. Daily Worker 7 8 9 5 9 14 15 10 Cum Resource 40 14 16 45 12 oc 5 7 9 14 15 Daily Worker 7 9 14 15 Cum Resource 40 70 115 121 133 od. 5 7 15 Daily Worker 8 7 8 9 6 4 T Cum Resource 40 49 72 126 90 72 18