Question: Given the following project Dur Res Act Pred (days) (worker A 4 2 B 2 1 C 5 3 D AB 5 3 E B.C

Given the following project Dur Res Act Pred

Given the following project Dur Res Act Pred (days) (worker A 4 2 B 2 1 C 5 3 D AB 5 3 E B.C 6 4 F DE 2 2 Which of the following is the correct daily resource and cumulative resource table. Select one: Daily 2 Worker 6 5 6 7 4 2 4 S 9 Cum Resource 6 11 17 24 28 30 O 2 a. 4 5 9 13 Daily Worker 5 6 7 4 2 5 9 13 Cum Resource 12 22 28 56 64 68 5 O b. Daily Worker 6 5 6 7 4 2 2 5 11 13 Cum Resource 12 20 30 63 44 26 9 13 13 Daily Worker 6 5 6 7 4 2 5 13 Cum Resource 12 10 6 28 8 4 O d. 2 5 9 11 Daily Worker 5 6 7 4 2 2 4 5 9 11 13 Cum Resource 12 10 28 8 4 9 11 13