Question: Given the following project network: a - 1 . Identify the critical path. A - C - E - F A - C - D

Given the following project network:
a-1. Identify the critical path.
A-C-E-F
A-C-D-F
A-B-D-F
a-2. Identify the earliest start and finish for each task. (Leave no cells blank - be certain to enter "O" wherever required.)
\table[[Task,\table[[Immediate],[Predecessors]],Earliest Start,Earliest Completion],[A,None,0,weeks,1,weeks],[B,A,1,weeks,7,weeks],[C,A,1,weeks,2,weeks],[D,B, C,7,weeks,16,weeks],[E,C,2,weeks,7,weeks],[F,D,E,15,weeks:,15,weeks]]
b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "0" wherever required.)
\table[[Task,\table[[Immediate],[Successors]],\table[[Latest],[Completion]],Latest Start],[F,None,,],[E,F,,],[D,F,,],[C,D,E,,],[B,D,,],[A,B,C,,]]
 Given the following project network: a-1. Identify the critical path. A-C-E-F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!