Question: Given the following project network: a-1. Identify the critical path. A-C-D-F A-B-D-F A-C-E-F a-2. Identify the earliest start and finish for each task. (Leave no


Given the following project network: a-1. Identify the critical path. A-C-D-F A-B-D-F A-C-E-F a-2. Identify the earliest start and finish for each task. (Leave no cells blank - be certain to enter "0" wherever required.) b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "O" wherever required.)