Question: Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate

Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate the EACfand the VACf. Based on your data, what is your assessment of the current status of the project? At completion?

Given the following project network, baseline, and status information, develop status reportsfor periods 2, 4, 6, 8 and complete the performance indexes table.Calculate the EACfand the VACf. Based on your data, what is your

\fStatus Report: Ending Perlod 2 ($000) Task % Complete EV AC PV CV SV A 75% 50% 12 1 1 Cumulative Totals 37 Status Report: Ending Perlod 4 ($000) Task % Complete EV AC SV A 100% 35 1 1 12 11 12 100% 24 Cumulative Totals 59 Status Report: Ending Perlod 6 ($000) Task % Complete EV IC 100% 35 100% 75% 1III112 11 1 1 1 12 1 1 1 1 1 12 0% 50% Cumulative Totals Status Report: Ending Perlod 8 ($000) Task Complete SV A 100% 35 100% 100% 32 1 1 1 1 1 12 11III12 111111 33% 20 100% 20 Cumulative Totals 131 Performance Indexes Summary Perlod EV AC PV SPI CPI PCI-B 11113 1III 1III 1111 EAC, = VAC, =\f

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!