Question: Given the following project network, baseline, and status information, develop status reports for ONLY periods 2, 4, 6, and complete the performance indexes table. Calculate



Given the following project network, baseline, and status information, develop status reports for ONLY periods 2, 4, 6, and complete the performance indexes table. Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion?
DO NOT COPY OTHER ANSWERS! SHOW ALL WORK AND CALCULATIONS!
LEGEND \begin{tabular}{|c|c|c|} \hline ES & ID & EF \\ \hline SL & & SL \\ \hline LS & DUR & LF \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline 10 & F & 12 \\ \hline 0 & & 0 \\ \hline 10 & 2 & 12 \\ \hline \end{tabular} Status Report: Ending Period 6 (\$000) Performance Indexes Summary Period246EVACPVSPICPIPCIB EACf=VACf=