Question: Given the following project network, baseline, and status information, develop status reports for periods 4 and 8. Calculate and report the final SV, CV, SPI,
Given the following project network, baseline, and status information, develop status reports for periods 4 and 8. Calculate and report the final SV, CV, SPI, CPI, PCIB, EACf and VACf. Based on your data, what is your assessment of the current status of the project (at the end of period 8),at completion?
PLease explain how to obtain Planned value(PV)
0 1 4 4 6 2 2 2 2 2 4 6 6 2 8 5 5 8 7 10 025 00 0 5 5 0 0 0 0 uh 3 8 8 2 10 Legend ESID EF 0 3 3 6 7 SL SL 1 1 1 1 1 3 4 4 4 LS 8 DUR LF 7 10 2 Task DURES 1 4 0 2 5 0 3 3 0 4 2 4 5 3 5 6 4 7 2 8 WOOO LF 6 5 4 8 8 8 10 Budget SL (PV) 3 6 B 9 2 $ 400 100 100 100 100 1500 200 300 400 400 200 1 800 100 400 300 400 200 200 900 200 400 300 1 1000 100 200 300 400 800 400 400 Total period PV 400 800 800 600 600 700 800 300 400 400 Cumulative PV 400 1200 2000 2600 3200 3900 4700 5000 5400 5800 UNO-NO-O SV Task % Complete 1 100% 2 80% 3 90% 4 0% 5 0% 6 0% Cumulative Totals Status Report: Ending Period 4 EV AC PV CV 400 1200 800 0 0 0 2400 SV Task % Complete 1 100% 2 100% 3 100% 4 100% 5 80% 6 100% Cumulative Totals Status Report: Ending Period 8 EV AC PV CV 400 1600 900 350 800 1000 5050 Performance Indices Summary CV SPI CPI PCIB SV Period 8 EAC VAC