Question: Use the following project information. Construct a network diagram using AON notation. Activity Activity Time (weeks) Immediate Predecessor(s) A 3 none B 4 A C

Use the following project information. Construct a network diagram using AON notation.

Activity Activity Time (weeks) Immediate Predecessor(s)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F