Question: Use the following project information. Construct a network diagram using AON notation. Activity Activity Time (weeks) Immediate Predecessor(s) A 3 none B 4 A C
Use the following project information. Construct a network diagram using AON notation.
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 3 | none |
| B | 4 | A |
| C | 2 | B |
| D | 5 | B |
| E | 4 | C |
| F | 3 | D |
| G | 2 | E,F |