Question: Given the following schedule information: Activity Predecessor a (days) m (days) b (days) A -- 7 9 11 B A 1 2 3 C A

Given the following schedule information:

Activity Predecessor a (days) m (days) b (days)
A -- 7 9 11
B A 1 2 3
C A 7 8 9
D B 2 5 11
E C 2 3 4
F C 1 4 8
G D,E 6 7 8
H F,E 2 6 9

  • Create a PERT schedule using Microsoft Excel. Use the relationships indicated, a start date of 4/10/2022, and the "a", "m", and "b" values given. What is the Expected Finish Date of the Project based upon the PERT calculations?