Question: Given the following schedule information: Activity Predecessor a (days) m (days) b (days) A -- 7 9 11 B A 1 2 3 C A
Given the following schedule information:
| Activity | Predecessor | a (days) | m (days) | b (days) |
| A | -- | 7 | 9 | 11 |
| B | A | 1 | 2 | 3 |
| C | A | 7 | 8 | 9 |
| D | B | 2 | 5 | 11 |
| E | C | 2 | 3 | 4 |
| F | C | 1 | 4 | 8 |
| G | D,E | 6 | 7 | 8 |
| H | F,E | 2 | 6 | 9 |
- Create a PERT schedule using Microsoft Excel. Use the relationships indicated, a start date of 4/10/2022, and the "a", "m", and "b" values given. What is the Expected Finish Date of the Project based upon the PERT calculations?