Question: Given the following small project for an AOA network, table [ [ Activity , Immediate Predecessor ( s ) , Time Duration ( days

Given the following small project for an AOA network,
\table[[Activity,Immediate Predecessor(s),Time Duration (days)],[A,D, E,10],[B,A,9],[C,A,4],[D,None,8],[E,None,6]]
How many nodes are there?
Keep your own AOA graph.
Select one:
a.6 nodes
b.4 nodes
c.5 nodes
d.7 nodes
e.8 nodes