Question: Given the following small project for an AOA network: table [ [ Activity , Immediate Predecessor ( s ) , Time Duration ( days

Given the following small project for an AOA network:
\table[[Activity,Immediate Predecessor(s),Time Duration (days)],[A,D,7],[B,D,6],[C,A, B,5],[D,None,4],[E,D,13]]
How many dummy arc(s) in this AOA network should be there totally?
Select one:
a. two dummy arcs
b. no dummy arc
c. four dummy arcs
d. one dummy arc
e. three dummy arcs
 Given the following small project for an AOA network: \table[[Activity,Immediate Predecessor(s),Time