Question: Given the following small project for an AOA network, table [ [ Activity , Immediate Predecessor ( s ) , Time Duration ( days

Given the following small project for an AOA network,
\table[[Activity,Immediate Predecessor(s),Time Duration (days)],[A,D, E,10],[B,A,9],[C,A,4],[D,None,8],[E,None,6]]
What is the critical length?
Keep your own AOA graph.
Select one:
a.23 days
b.25 days
c.27 days
d.28 days
e.20 days
 Given the following small project for an AOA network, \table[[Activity,Immediate Predecessor(s),Time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!