Question: Given the following small project, the critical path is days. table [ [ Activity , table [ [ Immediate ] , [ Predecessor

Given the following small project, the critical path is days.
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Time],[(days)]]],[A,--,8],[B,A,4],[C,-,10]]
10
4
12
22
 Given the following small project, the critical path is days. \table[[Activity,\table[[Immediate],[Predecessor]],\table[[Time],[(days)]]],[A,--,8],[B,A,4],[C,-,10]]