Question: Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 15 13 20000 26000 B A 12 12 25000 25000 C B

 Given the following table: Activity Predecessor Time Cost Normal Crashed NormalCrashed A 15 13 20000 26000 B A 12 12 25000 25000

Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 15 13 20000 26000 B A 12 12 25000 25000 C B 15 13 30000 38000 D -ww 15 12 30000 36000 E D 15 12 17000 26000 EL F E 15 12 23000 35000 G 16 13 50000 62000 H G 16 12 40000 60000 H 16 9 45000 87000 5. The crashed cost of finishing the project in 42 days, by filling template 3 (7m)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!