Question: Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed 14 10 20000 26000 B A 18 14 25000 33000 C B 16

Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed 14 10 20000 26000 B A 18 14 25000 33000 C B 16 12 30000 40000 15 12 30000 39000 ITA D 15 12 17000 27000 F E 15 11 23000 39000 G --- 13 12 50000 56000 H G 17 16 40000 45000 H 12 12 45000 45000 LIVE The normal time and the normal cost of the project. (2 m) 2. The crashed time of the project (1 m) 3. Fill template 1 (slopes), (4 m) 4. The crashed cost of the project using method one by filling template 2 (Zm)