Question: legg.com constructor - ... W Micro Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed 15 13 20000 26000 B. A 12

legg.com constructor - ... W Micro Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed 15 13 20000 26000 B. A 12 12 25000 25000 C B 15 13 30000 38000 15 12 30000 36000 E D 15 12 17000 26000 IF E 15 12 23000 35000 G 16 13 50000 62000 G 16 12 40000 60000 U H 16 9 45000 87000 LIVE 1. The normal time and the normal cost of the project. (2m) 2. The crashed time of the project (1m) 3. Fill template 1 (slopes), (4 m) 4. The crashed cost of the project using method one, by filling template 2_(7m)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
