Question: Given the following table, set up AOA and then answer the following 4 questions. Note: You need to completely comply with the six rules of
Given the following table, set up AOA and then answer the following 4 questions. Note: You need to completely comply with the six rules of AOA while setting up AOA.
| Activity | Immediate Predecessor(s) | Time Duration (days) |
| A | C,D | 4 |
| B | F | 5 |
| C | E | 2 |
| D | F | 7 |
| E | NONE | 4 |
| F | NONE | 3 |
(1) There Should be how many paths? (2) There should be how many dummy arc(s) in the AOA? (3) Compute the critical length in days (4) There should be how many non-critical activities in the project?