Question: Given the following table, set up AOA and then answer the following 4 questions. Note: You need to completely comply with the six rules of

Given the following table, set up AOA and then

Given the following table, set up AOA and then answer the following 4 questions. Note: You need to completely comply with the six rules of AOA while setting up AOA. Activity Immediate Predecessor(s) Time Duration (days) A C,D B F 5 E N D F 7 E None 4 F F None 3 (1) There should be _paths. (2) There should be _dummy arc(s) in the AOA. (3) Compute the critical length =- _days. (4) There should be _non-critical activities in the project