Question: Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D
Given the following task time estimates (HOURS), Task Time Predecessor
A 40
B 20
C 25 A
D 19 A, B
E 25 C, D
F 24 E
G 18, F
a. How long is the project length? [ Select ]
b. What tasks form the critical path? [ Select ]
c. What is the LS/LF for activity D.? [ Select ] .
d. How much slack is there in activity C? [ Select ] How much slack in activity D? [ Select ]
e. What if activity D. was delayed by 6 hours, what would be the project length and critical path? [ Select ]
f. Referring to letter e., how much slack would be in activity B.?