Question: Given the following tasks for a project with their durations ( in days ) and dependencies, calculate the earliest start ( ES ) , earliest
Given the following tasks for a project with their durations in days and
dependencies, calculate the earliest start ES earliest finish EF latest start
LS latest finish LF and float slack for each task:
Task Duration days Dependencies
A None
B A
C A
D B C
E B
F D E
Calculate ES EF LS LF and float for each task.
Identify the critical paths for the project.