Question: Given the following tasks for a project with their durations ( in days ) and dependencies, calculate the earliest start ( ES ) , earliest

Given the following tasks for a project with their durations (in days) and
dependencies, calculate the earliest start (ES), earliest finish (EF), latest start
(LS), latest finish (LF), and float (slack) for each task:
Task Duration (days) Dependencies
A 5 None
B 7 A
C 3 A
D 6 B, C
E 4 B
F 2 D, E
Calculate ES, EF, LS, LF, and float for each task.
Identify the critical path(s) for the project.