Question: Given the following time chart table [ [ Activity , Immediate Predecessor ( s ) , Time ( Days ) ] , [ -

Given the following time chart
\table[[Activity,Immediate Predecessor (s),Time (Days)],[-,5],[B,A,2],[C,A,4],[D,B,5],[E,B,5],[F,C,5],[G,E, F,2],[H,D,3],[I,G, H,5]]
(1) Draw the network diagram
(2) What is the critical path.
(3) What is the project completion time.
(4) Slack time for each activity
 Given the following time chart \table[[Activity,Immediate Predecessor (s),Time (Days)],[-,5],[B,A,2],[C,A,4],[D,B,5],[E,B,5],[F,C,5],[G,E, F,2],[H,D,3],[I,G, H,5]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!