Question: Given the following highway rerouting project, Activity Immediate Predecessor Activity Time ( months ) A: Schedule crew 4 B: Schedule equipment 6 C: Plan new
Given the following highway rerouting project,
Activity Immediate Predecessor Activity Time months
A: Schedule crew
B: Schedule equipment
C: Plan new route
A
D: Costs meet budget?
B
E: Inform public
C B
F: Put out signs
C B
G: Begin rerouting
D E
Draw the network.
Find the ESs, LSs and slacks.
Find the critical path.
If the project has a year deadline for reopening, should we consider crashing some activities? Explain.