Question: Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time ( te ) estimate?
Given the following time estimates: Optimistic days, Pessimistic days, and most likely days, what is the expected time te estimate?
Question Select one:
a
days
b
days
c
days
d
days
e
week, not counting weekends
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
