Question: Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time ( te ) estimate?

Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time (te) estimate?
Question 22Select one:
a.
6 days
b.
4 days
c.
3 days
d.
4.5 days
e.
1 week, not counting weekends

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!