Question: Given the forecast and booked orders shown in the table below, and a beginning inventory of 2 5 , what is the master production schedule

Given the forecast and booked orders shown in the table below, and a beginning inventory of 25, what is the master production schedule quantity for period 4 if you want to end period 4 with 0 inventory?
Period 1234
Forecasted Demand 70656055
Booked Orders 80603050
Projected ending inventory
Master production schedule 75
50
65
Available to Promise 0
Group of answer choices
40
50
70
35

Step by Step Solution