Question: Given the forecast and booked orders shown in the table below, and a beginning inventory of 2 5 , what is the master production schedule
Given the forecast and booked orders shown in the table below, and a beginning inventory of what is the master production schedule quantity for period if you want to end period with inventory?
tablePeriodForecasted Demand,Booked Orders,Projected ending inventory,,,,Master production schedule,Alaailable to Promise,