Question: Given the forecast and booked orders shown in the table below, and a beginning inventory of 25, what is the master production schedule quantity
Given the forecast and booked orders shown in the table below, and a beginning inventory of 25, what is the master production schedule quantity for period 4? Period 1 Forecasted Demand 70 Booked Orders 80 256 3 4 65 60 55 50 30 10 Projected ending inventory Master production schedule 55 Available to Promise 0
Step by Step Solution
There are 3 Steps involved in it
o calculate the master production schedule MPS quantity for period 4 we need to consider the for... View full answer