Question: Given the information below, complete the materials requirements planning (MRP) record. What are net requirements for weeks 5 and 7? What weeks they are released?
Given the information below, complete the materials requirements planning (MRP) record.
What are net requirements for weeks 5 and 7? What weeks they are released?
| Lot for Lot is ONLY used | Safety Stock: 0 units |
| Lead Time = 1 week | Current On-Hand Quantity = 50 units |
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirement |
|
|
|
| 300 |
| 200 |
|
| Projected On Hand 50 |
|
|
|
|
|
|
|
|
| Net Requirements |
|
|
|
|
|
|
|
|
| Planned Receipts |
|
|
|
|
|
|
|
|
| Planned Order Release |
|
|
|
|
|
|
|
|