Question: There are six jobs as below. The processing time (in days) and due date for each job are below. Job - Processing Time (days) 2

There are six jobs as below. The processing time
There are six jobs as below. The processing time (in days) and due date for each job are below. Job - Processing Time (days) 2 12 4 10 5 Due Date (days from present time) 7 16 4 15 10 18 00 e Please use SPT (shortest processing time) priority rule to calculate: (a) the average flow time =108/6=18 (b) average tardiness-53/6-8.83 (c) average number of jobs at the work center 108/41 -2.63