Question: Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that
Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less. Refer to the standard normal table
| Activity | Expected Time (weeks) | Variance | |
| A | 4.0 | 0.75 | |
| B | 6.0 | 0.69 | |
| C | 4.0 | 0.25 | |
| D | 12.0 | 1.78 | |
| E | 7.0 | 2.10 | |
| F | 8.5 | 2.55 | |
| G | 5.0 | 0.69 | |
Part 2
The probability that this path will take more than
20 weeks to complete is _____ enter your response here.
(Enter your response rounded to four decimal
places.)