Question: Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that

Given the information below, estimate the

Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less. Refer to the standard normal table. Activity A B D E F G TMU0 > Expected Time (weeks) 4.0 5.0 3.0 11.5 6.0 9.0 4.0 O O O O O O Variance 1.00 0.96 0.25 1.78 2.25 2.55 0.49 The probability that this path will take more than 20 weeks to complete is to four decimal places.) (Enter your response rounded