Question: Given the information below, how long is the Critical Path? table [ [ Activity , Time,Predecessor ] , [ A , 2 , -

Given the information below, how long is the Critical Path?
\table[[Activity,Time,Predecessor],[A,2,-],[B,3,-],[C,5,A],[D,4,B],[E,7,C,D],[F,2,D],[G,9,C],[H,6,G,E],[I,5,E,F],[J,7,H,I]]
26
50
27
29
21
 Given the information below, how long is the Critical Path? \table[[Activity,Time,Predecessor],[A,2,-],[B,3,-],[C,5,A],[D,4,B],[E,7,C,D],[F,2,D],[G,9,C],[H,6,G,E],[I,5,E,F],[J,7,H,I]]