Question: Given the information below, use the least unit cost lot sizing method to determine the production quantity for week 1 . ( Slides 4 2

Given the information below, use the "least unit cost" lot sizing method to determine the production quantity for week 1.(Slides 42-43)
Weeks Quantity Ordered Carrying Cost Order Cost Total Cost
11500 $0 $250 $250
1-22500 $50 $250 $300
1-33500 $150 $250 $400
1-44000 $225 $250 $475
1-56500 $725 $250 $975
1-68000 $1,100 $250 $1,350
Group of answer choices
6500
2500
8000
1500
3500
4000